FE daily problem for October 8, 2026 (Effective stress)

This is the FE practice problem that Engineer Exam Lab members worked on October 8, 2026. The topic is effective stress, from the FE Civil exam specification. Try it with the FE Reference Handbook open before you read on. The worked solution below gives the handbook section and page, the equation, every substitution with units, a size check, and the mistake behind each wrong answer.

The problem

Daily problem · FE Civil, Effective stress

A soil profile has 13 ft of sand over 14 ft of clay. The water table is 8 ft below the ground surface. The sand has a moist unit weight of 117 lb/ft³ above the water table and a saturated unit weight of 126 lb/ft³ below it. The clay has a saturated unit weight of 125 lb/ft³. Use γw = 62.4 lb/ft³. The vertical effective stress at the middle of the clay layer is most nearly:

  • A 1,760 lb/ft²
  • B 1,690 lb/ft²
  • C 2,440 lb/ft²
  • D 943 lb/ft²

Handbook: Civil Engineering, Geotechnical, Effective stress, FE Reference Handbook 10.6

Commit to an answer before you scroll. Writing the given values with their units first is the fastest way to spot what the question really asks for.

Worked solution, step by step

  • Answer: B (1,690 lb/ft²)
  • Given: H1 = 13 ft, dw = 8 ft, H2 = 14 ft, γm = 117 lb/ft³, γsat,sand = 126 lb/ft³, γsat,clay = 125 lb/ft³, γw = 62.4 lb/ft³
  • Find: vertical effective stress σ’ at the middle of the clay (lb/ft²)
  • Handbook: Civil Engineering, Geotechnical, Effective stress, page 269
  • Equation: σ' = σ - u; σ = Σ(γ·thickness) down to the point; u = γw × (depth below the water table)

Substitute, keeping the units on every value:

  1. Depth to the middle of the clay: z = H1 + H2/2 = 13 + 7 = 20 ft
  2. Total stress: σ = γm·dw + γsat,sand·(H1 - dw) + γsat,clay·(H2/2) = (117)(8) + (126)(5) + (125)(7) = 2,441 lb/ft²
  3. Pore-water pressure: u = γw(z - dw) = (62.4 lb/ft³)(12 ft) = 748.8 lb/ft²
  4. σ' = σ - u = 2,441 - 748.8 = 1,690 lb/ft²

Result: 1,690 lb/ft², 3 significant figures.

Check: With buoyant unit weights below the water table, γm·dw + (γsat,sand - γw)(H1 - dw) + (γsat,clay - γw)(H2/2) = 1,690 lb/ft², the same answer; units (lb/ft³)(ft) = lb/ft².

Why each wrong option is wrong

Every wrong option on this problem comes from a named mistake, so a wrong pick tells you exactly what to fix:

  • A (1,760 lb/ft²): used the saturated unit weight for the whole sand layer, including the part above the water table.
  • C (2,440 lb/ft²): is the total stress; the pore-water pressure u was not subtracted.
  • D (943 lb/ft²): used buoyant unit weights below the water table and then subtracted u again.

Where this is in the FE Reference Handbook

This problem uses Civil Engineering, Geotechnical, Effective stress, page 269 of FE Reference Handbook 10.6. The handbook is a free PDF in MyNCEES, and on exam day you search the same document on screen, so practice finding the section with the search box instead of from memory. Search for the name of the quantity you need, not the symbol, and check the page heading before you copy an equation.

How to approach problems like this

Work the number out before you look at the options. The wrong options are built from real mistakes, so a value that matches one of them proves nothing on its own. Write the given values with units, find the equation in the handbook with the search box, and substitute with the units attached. When your result lands on an option, run a quick size check: is the magnitude reasonable for the situation, and do the units reduce to what the question asks for? If your result falls between two options, look for a unit conversion you skipped.

Whatever the result, log it. A short error log with one line per missed problem (the topic, the mistake named in the solution, and the handbook page) shows within a few weeks which habits cost you points, and it turns review time into targeted practice instead of rereading.

For ten more problems on this topic, each with a full solution, see the effective stress practice set. Every past daily problem is in the daily problem archive, one page per day.

Frequently asked questions

Is this a real FE exam question?

No. It is an original problem that our problem engine generated from the formulas in the FE Reference Handbook and checked by code before it was posted. Real exam questions are confidential, and the agreement every examinee accepts forbids sharing them.

Why does this problem appear here a day late?

Members of Engineer Exam Lab get each problem first, in the morning, and the worked solution the same evening. The problem and its solution come to this public archive the next day.

How should I use the worked solution?

Compare your work with it line by line, not only the final answer. If you picked a wrong answer, find the note that matches it above; each one names the exact mistake, which is the habit to fix before exam day.

Sources

  1. NCEES FE Reference Handbook 10.6 (free PDF in MyNCEES). Retrieved October 3, 2026.
  2. NCEES FE Civil CBT exam specifications (PDF). Retrieved October 3, 2026.